Finance Minister Dr. Cassiel Ato Forson has announced a combined GH¢1.57 billion in the 2027 budget to revive two of Ghana’s most politically sensitive stalled market projects and to build a new modern regional market in the capital.

Date Created : 11/13/2026 : Story Author : Dominic Shirimori/Ghanadistricts.com

Presenting the 2027 Budget Statement to Parliament, Dr. Forson allocated GH¢685 million towards the completion of Kejetia Market Phase 2 in Kumasi and GH¢200 million for the completion of the Takoradi Market project in the Western Region. A separate GH¢685 million was earmarked for the construction of a modern Greater Accra Regional Market at New Agbogbloshie, signalling a major push to modernise trading infrastructure in all three regions.

Kejetia Phase 2: Stalled for Two Years at 58% Completion

The Kumasi project, awarded in December 2018 at a contract sum of €248 million, had reached 58.22 percent completion before work was suspended in early 2024 over funding and contractor-related disputes. The cost has since ballooned to over €305 million as the government moves to restart and finish the delayed works.

Contractors are scheduled to return to the site in October 2026, with completion projected for mid-2027 or by the end of the year. The four-level structure is designed to accommodate 10,528 trading units alongside essential public services. Revenue from Phase I currently stands at about GH¢89 million, far below initial projections intended to self-finance subsequent phases.

Takoradi Market: 81% Complete but Suspended Since 2023

The Takoradi Market Circle redevelopment, initiated in April 2020 at a cost of €48 million, was expected to be completed by 2023 but was suspended in early 2023 following Ghana’s debt restructuring programme. The project, being executed by Italian contractor Contracta Costruzioni Italia SLR, was about 81.62 percent complete when work stopped.

The government has so far committed €41.7 million to the project, covering part of the original contract sum and costs incurred from the prolonged suspension. A new funding arrangement is being pursued to settle the outstanding €18 million owed to the contractor, with work expected to resume within two months and completion targeted within a year after the contractor returns to the site.

The stalled project has taken a heavy toll on traders relocated to a temporary site five years ago. Traders have protested, threatened to suspend market toll payments, and petitioned Parliament over what they describe as “harrowing” financial and emotional hardship, alleging that some affected traders have died or become bedridden.

New Agbogbloshie: A Modern Greater Accra Regional Market

The GH¢685 million allocation for the Greater Accra Regional Market at New Agbogbloshie is intended to deliver a modern, integrated trading hub in the capital. The project, conceived as a 24-hour economy market, requires approximately four acres of land, with 3.2 acres already identified, including plots within the existing Yam Market area.

The Accra Metropolitan Assembly has clarified that the project aims to deliver modern commercial infrastructure, improve sanitation and safety, organise local trade, and create employment opportunities within the capital. The proposed market is expected to integrate traditional trading with modern commercial infrastructure, including shops, stalls, warehouses, cold stores, a supermarket, restaurants, and social amenities such as a hospital, police station, and fire station.

However, the project has faced consultation challenges, with the government putting the redevelopment exercise on hold in September 2026 to allow for further engagement with the AMA and affected traders. The 2027 allocation signals that the project is back on the front burner.

Political Test

The three market projects carry significant political weight. Kejetia and Takoradi were both flagship projects of the previous New Patriotic Party administration, and their prolonged stall has become a symbol of abandoned promises for traders and residents in Kumasi and Sekondi-Takoradi. The new Agbogbloshie market, meanwhile, is a fresh commitment in the capital.

For Dr. Forson and the Mahama administration, the 2027 allocations represent both an opportunity and a test: whether the money approved in Parliament translates into contractors on site, cranes in the air, and traders back in modern sheds — or whether the projects remain, as critics allege, monuments to Ghana’s chronic implementation gap.