Talensi DCE Inspects Progress of TongoYameriga, Sheaga Duusi and Pelungu Road Project

The District Chief Executive for Talensi in the Upper East Region, John Millim Nabwomya, has inspected ongoing works on the Tongo Yameriga Sheaga, Duusi Pelungu road project to assess progress and ensure the timely execution of the infrastructure development.

Date Created : 11/9/2026 : Story Author : News Ghana/Ghanadistricts.com

The inspection, conducted on September 4, 2026, formed part of the Assembly's monitoring efforts to ensure that the contractor, ARACO Company Limited, delivers the project according to the required standards.


During the visit, the  DCE interacted with tipper truck drivers engaged by the contractor, who were transporting quarry stones and sand to various sections of the road for the construction of concrete gutter and also visited the contractor's campsite, where he was briefed on the mobilisation of essential construction equipment and materials, including concrete gutter moulds, concrete mixers and cement.


In a telephone conversation with the contractor, the DCE was informed that the company had prioritised the transportation of construction materials to different sections of the road ahead of major excavation works. The contractor explained that moving heavy-duty trucks along the road would become difficult once excavation activities commenced. Consequently, the decision was taken to transport and position the necessary materials at strategic locations before the commencement of that phase of construction.


The mobilisation exercise had already extended beyond Tongo through the Sheaga stretch, with transportation continuing towards other sections of the project.


Mr. Nabwomya expressed satisfaction with the progress of preparations and reiterated the Assembly's commitment to closely monitoring the project to ensure steady implementation and adherence to the required construction standards.

The 36kilometre Tongo-Sheaga-Pelungu Road Upgrade Project is an important infrastructure intervention expected to improve transportation and connectivity among communities along the corridor.


When completed, the road is expected to facilitate the movement of people, agricultural produce and other goods, reduce transportation difficulties and improve access to essential services and economic opportunities.

The project, together with the installation of solar streetlights along sections of the corridor, is also expected to improve visibility, road safety and security for residents and other road users.