Korle Klottey MCE Inspects Development Projects, Assesses Progress of Ongoing Works

The Municipal Chief Executive (MCE) for Korle Klottey, Hon. Alfred Allotey-Gaisie, has inspected selected development projects across the municipality to assess their progress, quality of work and implementation status.

Date Created : 11/20/2026 : Story Author : Mary Ayertey/Ghanadistricts.com

The inspection was conducted with Heads of Department and technical officers of the Korle Klottey Municipal Assembly as part of efforts to strengthen project monitoring and ensure the timely delivery of infrastructure.

Projects inspected included a two-storey kindergarten block at Osu Manhean, which was 95 per cent complete, and a CHPS compound with a dental clinic at Adabraka, recording 90 per cent completion.

The team also inspected water supply systems and storage facilities being provided for selected institutions, which were 80 per cent complete, as well as the painting of five institutional facilities, with progress estimated at 70 per cent.

Other projects included improvement works at the Osu Library, which had reached 98 per cent completion, and a two-storey toilet facility with 20 toilet seats and 20 bathroom units at Osu Doku, which had been completed.

During the exercise, the MCE and his team engaged contractors on the progress of work, identified outstanding tasks and discussed measures to address challenges that could affect the completion of the projects.

The inspection forms part of the Assembly's commitment to effective project supervision, quality infrastructure delivery, accountability and value for money.

The Assembly reaffirmed its determination to ensure that ongoing projects are completed to the required standards and made available to residents and beneficiary institutions.