SOCIAL
President Akufo-Addo commissions Ghana’s first micro-hydro power station at alavanyo
Date Created : 11/23/2020 12:00:00 AM : Story Author : Ghanadistricts.com
The origins of the project date back to 2005, when the Ministry of Energy, under the Government of President John Agyekum Kufuor, entered into a Memorandum of Understanding with the United Nations Industrial Development Organization (UNIDO) and International Network on Small Hydro Power of China (IN-SHP) to undertake studies geared towards the development of Small Hydro Power potentials in the country.
According to the President, before the project could be operationalized in the twenty-two (22) sites identified, the NPP lost the 2008 elections, and, “like many other important initiatives of the Kufuor Government, this project was also abandoned”.
Indeed, the Tsatsadu project was initially designed as a 30kW stand-alone system, but was redesigned and upgraded to a 45kW grid-connection system based on the outcome of the additional studies.
The President assured the Togbega of Alavanyo that the road leading up to the Tsatsadu Generating Station is “under active development, and will be done”, stressing that “indeed, Alavanyo, it shall be well”.
The President, thus, urged residents of Tsatsadu, Alavanyo, and, indeed, Hohoe to vote massively for him and for John-Peter Amewu, “so we can do more for you.”